The three things people confuse
| Request | What PG&E does | When you need it |
|---|---|---|
| Turn off / close account | Stops billing; meter stays | Never sufficient for demolition |
| Temporary disconnect | Service de-energized, facilities stay | Remodels, roof work near lines |
| Permanent disconnect (termination) | Meter and drop/lateral removed; gas cut and capped | Demolition. This is the one the building department wants |
How it runs
- Submit the permanent disconnect request in Your Projects — electric and gas are separate. Have the account/meter numbers, the site plan, and the demo permit number or application.
- PG&E schedules field work. Electric: meter pull and drop/lateral removal. Gas: cut and cap at the property line, or at the main if the service is being abandoned.
- Get the confirmation in writing — the notification number and the date the work was completed. The building department will ask.
- Demolition, then the new-service applications (which you should already have filed).
Why disconnects stall teardowns
- Filed late. The request goes in when the excavator is booked. Then everyone waits.
- Gas cut location. Cut at the property line versus at the main is a different scope and schedule — and it matters for the new gas service you'll want later.
- Shared or unclear services. Duplexes, rear units and old lots with a neighbor's drop crossing yours need a site walk first.
- Nobody owns the follow-up. Disconnects don't show up on anyone's schedule until they're late.
Questions builders ask
Do I need both electric and gas disconnected before demolition?
Yes, if both are present. They are separate PG&E requests with separate notification numbers, and the building department typically wants confirmation of both before the demo permit is finaled.
How long does a PG&E disconnect take?
PG&E does not publish a fixed timeline for permanent disconnects. The application step is covered by the CPUC 10-day average / 45-day maximum decision target; field work is scheduled after that. Plan weeks, and file when you apply for the demo permit.
Should I file the new service application before or after demolition?
Before. Standard-process design can take up to 60 business days. The disconnect and the new service are separate files that should run in parallel.