PG&E guide · new service

How long does PG&E take to connect new electric service?

The honest answer is "it depends which queue you're in." There are two, and most builders don't know which one they're standing in until month three.

Short answer. If your job qualifies for Express Connect (residential, up to 320A, overhead), PG&E's published average is about 100 calendar days from submission to energization: ~34 days to approval, ~66 more to the meter. Everything else runs on the standard process, where the CPUC target is 182 days average and 357 days maximum from approval — and PG&E's own reporting says roughly one project in six misses the average.

The two queues

Express ConnectStandard ("New Project") process
WhoResidential only. Panel changes/added load, new overhead electric service, ADU meter, overhead relocation — all up to 320A. Gas meter upgrades (residential & commercial). Overhead temp power ≤200A where infrastructure exists.Everything else: underground service, anything over 320A, commercial electric, line extensions, projects that fail the load assessment.
DesignLoad assessment at intake; PG&E job owner contacts you within ~5 business daysUp to 60 business days for PG&E design (or applicant design with a PG&E-qualified designer)
ConstructionScheduled after approval; you install the panel within 20 calendar daysUp to 60 business days after contract, payment and site readiness
Published time~34 days to approval + ~66 to energization ≈ 100 daysCPUC target 182 avg / 357 max from approval

What the CPUC now requires of PG&E

Since SB 410 (the Powering Up Californians Act) and CPUC Decision D.24-09-020, PG&E reports its energization performance twice a year against these targets:

What PG&E is doingApplies toAverage targetMaximum
Deciding on your applicationEvery application10 days45 days
Main-panel upgradePanel replacement / capacity increase30 days45 days
New service or line extensionElectric Rule 15182 days357 days
Service-line workElectric Rule 16182 days335 days
Combined Rule 15 + 16New extension plus service182 days306 days
EV charging infrastructureElectric Rule 29182 days335 days

Calendar days, counted from the day PG&E approves the request — not from the day you submit. Customer-caused delays (unpaid advances, missing permits, a panel that isn't installed) stop the clock. Source: CPUC D.24-09-020 targets for PG&E, SCE and SDG&E.

In its June 2025 reporting, PG&E met the 182-day average on about 84% of projects and the maximum on about 97%. That is the number to remember: roughly one project in six runs past six months, and the maximum is not a guarantee either.

What starts the clock — and what stops it

Since August 2025 PG&E's Your Projects portal shows a Project Tracker with five phases — application & intake, engineering & design, dependencies, site readiness, construction. It shows where you are. It doesn't tell you why you're stuck or who to call.

When it's late

  1. Your PG&E job owner, in writing, asking for a revised date and the name of the person accountable for it.
  2. Their supervisor at 48 hours without an answer.
  3. The Escalate Issue button in Your Projects (Project ID → Actions tab) and the Building & Renovation Services Center: 1-877-743-7782, Mon–Fri 7am–6pm.
  4. Past the CPUC maximum: a delayed-energization report to the CPUC. PG&E's division leadership pays attention to those.

Questions builders ask

Does the 182-day target start when I submit my application?

No. It starts when PG&E approves the request — after the application is complete. The application-decision step has its own target: 10 days average, 45 maximum.

Is Express Connect faster for everyone?

Only if you qualify and stay qualified. Residential, up to 320A, overhead. If the load calculation fails or documents arrive after the 19-day window, the job drops into the standard process.

Can I speed up a standard project?

Partly. Applicant Design (Rules 15/16) with a PG&E-qualified designer and an SQCA-prequalified installer takes design and trench/conduit work out of PG&E's queue on new extensions. PG&E still reviews, inspects and energizes.

Want PG&E off your desk?

MeterSet files, tracks and escalates PG&E work for Bay Area builders — new service, upgrades, temp power, disconnects. Flat fees. Weekly updates. 250+ utility engagements.

More PG&E guides

PG&E Express Connect: who qualifies, how long it takesThe ~100-day fast path for residential jobs up to 320A, and the two deadlines that knock you out of it.Upgrading to 200A or 400A with PG&EPanel upgrade, service upgrade, added load — which path you're on and what PG&E needs.PG&E temporary power for construction sitesWhen temp power is fast, when it isn't, and what to have ready before you apply.PG&E electric and gas disconnects for demolitionGetting services terminated before the demo permit — the step that stalls teardowns.
Sources. PG&E Building & Renovation Services (pge.com); PG&E Express Connect Customer Journey (PDF); PG&E Applicant Design Process (PDF); CPUC Decision D.24-09-020 and the June 2025 energization-timelines workshop deck (cpuc.ca.gov); PG&E Electric Rules 15, 16 and 29. Figures are PG&E's published averages and CPUC targets as of September 2026 and can change.