PG&E guide · temporary power

PG&E temporary power for construction sites

Temp power is either the easiest PG&E job on your project or the one that quietly costs you a month. The difference is whether a pole and transformer are already within reach.

Short answer. Overhead temporary power up to 200A, where PG&E infrastructure already exists at the site, qualifies for Express Connect — PG&E's published averages are ~34 days to approval and ~66 to energization. Anything larger, underground, or needing new facilities runs the standard process, and you should plan on months, not weeks.

Fast or slow — the three questions

  1. Is there existing overhead infrastructure at the site? A pole with secondary within reach. If PG&E has to set a pole or extend a line, it's not Express Connect.
  2. Is the request 200A or less? Larger temp services are standard process.
  3. Overhead, not underground. Underground temp power is standard process.

What to have ready before you apply

Sequencing it with the rest of the job

MeterSet handles temp power as a flat-fee job — application through connection — and can arrange temp pole install, removal and rental as an add-on.

Questions builders ask

How long does PG&E temp power take?

If it qualifies for Express Connect (overhead, ≤200A, existing infrastructure), PG&E's published averages are about 34 days to approval plus about 66 days to energization. Otherwise it is standard process.

Does PG&E install the temp pole?

No. Your electrician installs the pole, socket and panel; the local building department inspects it; PG&E connects the service.

Can I skip temp power and just get permanent service early?

Sometimes, on a panel-upgrade or same-location rebuild. On a teardown with a new service route, permanent service is usually months out — temp power bridges it.

Want PG&E off your desk?

MeterSet files, tracks and escalates PG&E work for Bay Area builders — new service, upgrades, temp power, disconnects. Flat fees. Weekly updates. 250+ utility engagements.

More PG&E guides

How long does PG&E take for new electric service?Application to energization, by project type — and what the CPUC now requires.PG&E Express Connect: who qualifies, how long it takesThe ~100-day fast path for residential jobs up to 320A, and the two deadlines that knock you out of it.Upgrading to 200A or 400A with PG&EPanel upgrade, service upgrade, added load — which path you're on and what PG&E needs.PG&E electric and gas disconnects for demolitionGetting services terminated before the demo permit — the step that stalls teardowns.
Sources. PG&E Building & Renovation Services (pge.com); PG&E Express Connect Customer Journey (PDF); PG&E Applicant Design Process (PDF); CPUC Decision D.24-09-020 and the June 2025 energization-timelines workshop deck (cpuc.ca.gov); PG&E Electric Rules 15, 16 and 29. Figures are PG&E's published averages and CPUC targets as of September 2026 and can change.