Fast or slow — the three questions
- Is there existing overhead infrastructure at the site? A pole with secondary within reach. If PG&E has to set a pole or extend a line, it's not Express Connect.
- Is the request 200A or less? Larger temp services are standard process.
- Overhead, not underground. Underground temp power is standard process.
What to have ready before you apply
- Site plan marking the temp pole location relative to PG&E's pole
- Panel size and the loads you'll run (tools, trailer, dewatering, heaters)
- Permit status — the AHJ inspects the temp pole before PG&E connects
- Who owns the pole install: your electrician installs the temp pole, meter socket and panel; PG&E connects
Sequencing it with the rest of the job
- Teardowns: the permanent disconnect of the old service and the temp power request are separate PG&E jobs. File both early; the disconnect gates demolition (how that works).
- Permanent service: file the permanent application while temp power is running. Standard-process design is up to 60 business days — start it the day you have the site plan.
- Removal: the temp service has to come off at the end. Schedule it with the permanent meter set, not after.
Questions builders ask
How long does PG&E temp power take?
If it qualifies for Express Connect (overhead, ≤200A, existing infrastructure), PG&E's published averages are about 34 days to approval plus about 66 days to energization. Otherwise it is standard process.
Does PG&E install the temp pole?
No. Your electrician installs the pole, socket and panel; the local building department inspects it; PG&E connects the service.
Can I skip temp power and just get permanent service early?
Sometimes, on a panel-upgrade or same-location rebuild. On a teardown with a new service route, permanent service is usually months out — temp power bridges it.