PG&E guide · service upgrades

Upgrading to 200A or 400A with PG&E

A 100A→200A upgrade and a 200A→400A upgrade look like the same job to a homeowner. To PG&E they are different queues, different timelines and different paperwork.

Short answer. A residential upgrade to 200A (or anything up to 320A) is normally an Express Connect job: ~34 days to approval, panel installed within 20 days, ~66 days to energization. A 400A / 320C service is over the ceiling and runs the standard process. The CPUC's target for the main-panel-upgrade step itself is 30 days average, 45 maximum; a full new service is 182 / 357.

Which job are you actually doing?

You call itPG&E calls itPath
Panel swap, same ampsPanel changeExpress Connect (residential)
100A → 200A, overheadService upgrade, overheadExpress Connect
100A → 200A, undergroundService upgrade, undergroundStandard (underground is not Express Connect)
Added load for EV / ADU / heat pump, no panel workAdded loadExpress Connect if ≤320A and load passes
200A → 400A (320C)New service / upgrade over 320AStandard process; often Rule 16 service work

What PG&E wants in the package

On Express Connect, documents are due within 19 calendar days of submission if engineering review is required. Late means the standard queue.

Where upgrades stall

If you are an electrician: you don't have to own the PG&E file to keep the job. MeterSet runs the application, the follow-ups and the escalations; you do the electrical.

Questions builders ask

How long does a 200A upgrade take with PG&E?

On Express Connect, PG&E publishes about 34 days to approval and about 66 days from approval to energization — roughly 100 days if the package is complete and the panel goes in within 20 days of approval.

How long does a 400A upgrade take?

It runs the standard process. The CPUC target from approval is 182 days average, 357 maximum for new service; service-line-only work is 182 / 335.

Do I need a load calculation for a panel upgrade?

If PG&E requires engineering review, yes — and on Express Connect it has to pass for the project to stay on the fast path.

Want PG&E off your desk?

MeterSet files, tracks and escalates PG&E work for Bay Area builders — new service, upgrades, temp power, disconnects. Flat fees. Weekly updates. 250+ utility engagements.

More PG&E guides

How long does PG&E take for new electric service?Application to energization, by project type — and what the CPUC now requires.PG&E Express Connect: who qualifies, how long it takesThe ~100-day fast path for residential jobs up to 320A, and the two deadlines that knock you out of it.PG&E temporary power for construction sitesWhen temp power is fast, when it isn't, and what to have ready before you apply.PG&E electric and gas disconnects for demolitionGetting services terminated before the demo permit — the step that stalls teardowns.
Sources. PG&E Building & Renovation Services (pge.com); PG&E Express Connect Customer Journey (PDF); PG&E Applicant Design Process (PDF); CPUC Decision D.24-09-020 and the June 2025 energization-timelines workshop deck (cpuc.ca.gov); PG&E Electric Rules 15, 16 and 29. Figures are PG&E's published averages and CPUC targets as of September 2026 and can change.