What this checks
Since SB 410 and CPUC Decision D.24-09-020, PG&E reports its energization times against targets set by the CPUC. Most builders never see those numbers, so they do not know when to push. This tool compares your dates with them.
| Step | Average | Maximum | Clock starts |
|---|---|---|---|
| Decision on your application | 10 days | 45 days | Complete application received |
| Main-panel upgrade | 30 days | 45 days | Approval |
| Rule 16 service | 182 days | 335 days | Approval |
| Rule 15 line extension | 182 days | 357 days | Approval |
| Rule 15 + 16 combined | 182 days | 306 days | Approval |
| Rule 29 EV charging | 182 days | 335 days | Approval |
All calendar days. For Express Connect jobs (residential, up to 320A, overhead) PG&E's own published averages are about 34 days to approval and about 66 more to energization. PG&E publishes no fixed timeline for demolition disconnects.
If it is late
- Email your PG&E job owner. Ask for a revised date in writing and the name of the person accountable for it.
- No answer in 48 hours: go to their supervisor.
- Use Escalate Issue in PG&E Your Projects (Project ID, then the Actions tab).
- Past the CPUC maximum: report it to the CPUC through its energization delay form.
Or hand it to MeterSet: escalating stalled PG&E jobs is most of what we do.
Questions builders ask
How long does PG&E have to decide on my application?
The CPUC target is 10 calendar days on average and 45 at most, counted from when PG&E receives a complete application.
When does the CPUC energization clock start?
When PG&E approves your request, not when you submit it. Customer-side holds such as unpaid fees, missing permits or a panel that is not installed stop the clock.
What are the CPUC targets for new service?
Rule 16 service work: 182 days average, 335 maximum. Rule 15 line extensions: 182 average, 357 maximum. Combined Rule 15 and 16: 182 average, 306 maximum. Main-panel upgrades: 30 average, 45 maximum. All calendar days from approval.
What can I do if PG&E is past the target?
Ask your PG&E job owner in writing for a revised date and who is accountable for it, go to their supervisor after 48 hours without an answer, use Escalate Issue in Your Projects, and report the delay to the CPUC if it is past the maximum.