Mountain View, California

PG&E new service, upgrades and disconnects in Mountain View

What a Mountain View build or teardown needs from PG&E and from the city, in the order it happens.

Who serves Mountain View: Silicon Valley Clean Energy (SVCE) supplies the electricity, but PG&E owns the lines, delivers the power, handles new service requests and supplies gas. Every new service, upgrade and disconnect is still a PG&E job.

From city permit to PG&E meter in Mountain View

  1. City permit. Building permits go through Community Development (Building Division), using ePermitsMV.
  2. PG&E application. The new service, upgrade or disconnect is a separate application to PG&E. A complete package the first time is what keeps it moving.
  3. PG&E design and scheduling. PG&E assigns a job owner, designs the service and schedules its crews. This is where most jobs stall without follow-up.
  4. City final and release. Mountain View uses a utility release inspection: the inspector issues a utility release form that goes to PG&E so it can connect the new panel. Nothing happens at the meter until that release reaches PG&E.
  5. Meter set. PG&E sets the meter and energizes once it has the release and its own work is done.

Mountain View rules that affect PG&E work

New homes: 200A minimum

New single-family homes need at least a 200-amp service (City Code 8.51(C)). Size the PG&E application for it from the start.

Demolition

A demolition permit requires a letter from PG&E confirming gas and electric are disconnected. That letter is usually the long pole on a teardown.

Gas and pre-wiring

The gas-appliance ban was suspended on April 9, 2024. Since January 1, 2026, remodels and additions that install gas or propane equipment must include electric pre-wiring, which can push a job into a service upgrade.

Undergrounding

Required for subdivisions (Code 28.9.15).

What MeterSet handles in Mountain View

Questions Mountain View builders ask

What is a utility release in Mountain View?

After the electrical inspection passes, the inspector issues a utility release form that goes to PG&E. PG&E will not energize the new panel without it.

What do I need from PG&E to demolish a house in Mountain View?

A letter from PG&E confirming the gas and electric services are disconnected. The city requires it for the demolition permit.

Want PG&E off your desk?

MeterSet files, tracks and escalates PG&E work for Bay Area builders — new service, upgrades, temp power, disconnects. Flat fees. Weekly updates. 250+ utility engagements.

Other cities we cover

San JoséPG&E service, upgrades and disconnectsSunnyvalePG&E service, upgrades and disconnectsLos AltosPG&E service, upgrades and disconnectsMenlo ParkPG&E service, upgrades and disconnectsCupertinoPG&E service, upgrades and disconnectsSaratogaPG&E service, upgrades and disconnectsLos GatosPG&E service, upgrades and disconnectsCampbellPG&E service, upgrades and disconnectsRedwood CityPG&E service, upgrades and disconnectsSan MateoPG&E service, upgrades and disconnectsBurlingamePG&E service, upgrades and disconnects

PG&E guides

How long does PG&E take for new electric service?Application to energization, by project type — and what the CPUC now requires.PG&E Express Connect: who qualifies, how long it takesThe ~100-day fast path for residential jobs up to 320A, and the two deadlines that knock you out of it.Upgrading to 200A or 400A with PG&EPanel upgrade, service upgrade, added load — which path you're on and what PG&E needs.PG&E temporary power for construction sitesWhen temp power is fast, when it isn't, and what to have ready before you apply.PG&E electric and gas disconnects for demolitionGetting services terminated before the demo permit — the step that stalls teardowns.
Sources. SVCE service area; Mountain View same-day permits (utility release); Mountain View new single-family construction; Mountain View residential demolition; Mountain View green building and reach codes; PG&E Building & Renovation Services; PG&E Greenbook. City rules were checked against these pages in October 2026 and can change; confirm with the city before you design.