Saratoga, California

PG&E new service, upgrades and disconnects in Saratoga

What a Saratoga build or teardown needs from PG&E and from the city, in the order it happens.

Who serves Saratoga: Silicon Valley Clean Energy (SVCE) supplies the electricity, but PG&E owns the lines, delivers the power, handles new service requests and supplies gas. Every new service, upgrade and disconnect is still a PG&E job.

From city permit to PG&E meter in Saratoga

  1. City permit. Building permits go through Community Development (Building Division), using eTRAKiT; panel upgrades can also go through the city's Symbium express permits.
  2. PG&E application. The new service, upgrade or disconnect is a separate application to PG&E. A complete package the first time is what keeps it moving.
  3. PG&E design and scheduling. PG&E assigns a job owner, designs the service and schedules its crews. This is where most jobs stall without follow-up.
  4. City final and release. PG&E will not start new gas or electric service until permits and final inspections are complete, and many cities forward the inspection result to PG&E directly. In Saratoga an electrical service upgrade needs only a final inspection, so the PG&E side is usually the long pole, not the city.
  5. Meter set. PG&E sets the meter and energizes once it has the release and its own work is done.

Saratoga rules that affect PG&E work

Undergrounding

Saratoga's zoning code (Article 15-80) requires electric and communication lines to be underground citywide. There is a limited exception for an overhead drop to a structure that already has one, when no new poles are needed and the run is 500 feet or less. A new home usually means a trench; settle it before you design the service.

Electrification

The city repealed its mostly-electric requirement on September 18, 2024. Ordinance 414, effective January 1, 2026, allows mixed-fuel homes and adds electric-readiness rules for remodels, which can change your panel size.

What MeterSet handles in Saratoga

Questions Saratoga builders ask

Do I have to underground the electric service on a Saratoga new home?

Almost always. Saratoga requires electric lines to be underground citywide; the exception covers only an existing overhead drop that needs no new poles and runs 500 feet or less.

Does Saratoga still require all-electric new homes?

No. The mostly-electric requirement was repealed on September 18, 2024. Since January 1, 2026, Ordinance 414 allows mixed-fuel homes but adds electric-readiness rules for remodels.

Want PG&E off your desk?

MeterSet files, tracks and escalates PG&E work for Bay Area builders — new service, upgrades, temp power, disconnects. Flat fees. Weekly updates. 250+ utility engagements.

Other cities we cover

San JoséPG&E service, upgrades and disconnectsSunnyvalePG&E service, upgrades and disconnectsMountain ViewPG&E service, upgrades and disconnectsLos AltosPG&E service, upgrades and disconnectsMenlo ParkPG&E service, upgrades and disconnectsCupertinoPG&E service, upgrades and disconnectsLos GatosPG&E service, upgrades and disconnectsCampbellPG&E service, upgrades and disconnectsRedwood CityPG&E service, upgrades and disconnectsSan MateoPG&E service, upgrades and disconnectsBurlingamePG&E service, upgrades and disconnects

PG&E guides

How long does PG&E take for new electric service?Application to energization, by project type — and what the CPUC now requires.PG&E Express Connect: who qualifies, how long it takesThe ~100-day fast path for residential jobs up to 320A, and the two deadlines that knock you out of it.Upgrading to 200A or 400A with PG&EPanel upgrade, service upgrade, added load — which path you're on and what PG&E needs.PG&E temporary power for construction sitesWhen temp power is fast, when it isn't, and what to have ready before you apply.PG&E electric and gas disconnects for demolitionGetting services terminated before the demo permit — the step that stalls teardowns.
Sources. SVCE service area; SVCE member cities; Saratoga Building Division; Saratoga building inspection processes; Saratoga Code of Ordinances, Article 15-80; Saratoga Ordinance 414; PG&E Building & Renovation Services; PG&E Greenbook. City rules were checked against these pages in October 2026 and can change; confirm with the city before you design.